| 
            
 
             
             
             
Over the Martin
            Luther King Holiday, January 20, crews will follow
            their normal construction schedule. 
 
            Monday, January 20 - Friday, January 24  
 
            From 7 am to 8:30 am one lane travel with pilot cars and flaggers
            will be in place.  
             
            From 8:30 am to 11:30 am US-89 is closed to all traffic from MP 65
            - MP 68.  
             
            From 11:30 am to 6:00 pm one lane travel with pilot cars and
            flaggers will be in place. 
             
            From 6:00 pm to 7 am The roadway will be open to two lane travel. 
             
              | 
              
 | 
              
              | 
               
Excavation work is moving ahead at different areas
              on the project. Several trucks and earth moving equipment are
              operational during construction hours. 
 | 
              
 
   
            This week on the project crews will continue to pioneer temporary
            roads to allow for drilling equipment to have access. The drilling
            equipment will begin drilling for blasting operations when
            feasible. 
             
            A test blast could be conducted on the project this week pending
            approval by appropriate agencies. This blast will be coordinated
            with local officials and state fire officials. 
             
            Motorists will notice an increase in truck traffic. The added
            trucks will continue to move material from the dig sites to the
            dump sites. Most debris removed from the dig sites will be used as
            fill material in other areas on the project.  
             
            Work continues on a new box culvert near MP66. Crews are forming
            the new box and reinforcing the structure with rebar. Lengthening
            the structure will allow for the new alignment of the roadway and
            more efficiently handle run-off water.  
            
             
              | 
              
 | 
              
              | 
               
About 100,000 cubic yards of material will be
              moved from the roadway excavation to the dump sites on the
              project. The material dumped will shore-up the existing roadway
              and provide needed fill for the Kane County Water Conservancy
              District.  
 | 
              
 
 
 
            With the cultural history present in the construction area an
            Archeologist is on-site at all times during construction to assist
            with any sensitive operations. 
During an emergency situation where emergency
            responders need to travel through the construction zone they will
            be allowed to do so. The contractor will maintain a pathway through
            the project at all times for any emergency situations and will be
            coordinating with the Kane County Sheriff's office. 
 |